3. ISSUANCE OF BUILDING PERMIT (GOVERNMENT TO GOVERNMENT - COMPLEX)

PURSUANT TO RULE III - (PERMITS AND INSPECTION (SECTION 301) OF THE NATIONAL BUILDING CODE OF THE PHILIPPINES (PD 1096) – BUILDING PERMITS (No person, firm or corporation, including any agency or instrumentality of the govermnent shall construct, alter, repair, convert, use, occupy, move, demolish and add any building/structure or any portion thereof or cause the same to be done, without first obtaining a building permit therefor from the Building Official assigned in the place where the subject building/structure is located to be done. The prescribe application for building permit from (NBC form B-01) shall be used by all applicants.) Permits suplementary to a Building Official shall be applied for and issue by the Building Official. These include Ancillary and Accessory Permits.

Service Details

OFFICE OR DIVISION:

OFFICE OF THE BUILDING OFFICIAL

CLASSIFICATION:

COMPLEX

TYPE OF TRANSACTION:

G2G - Government to Government

WHO MAY AVAIL:

ALL RESIDENTS OF MANOLO FORTICH,ALL INVESTORS

CHECKLIST OF REQUIREMENTS:

WHERE TO SECURE

1. Four (5) Copies (Blue prints/A3 PLANS) of Building Plans signed and sealed by : a. Civil Engineer b. Architect c. Master Plumber d. Sanitary Engineer e. Professional Electrical Engineer f. Professional Mechanical Engineer g. Professional Electronics Engineer h. Geodetic Engineer i. Agricultural Engineer

Professional Practitioners/Engineers

ATTACHED WITH THE FOLLOWING:

a. Site Development Plan, Lot Plan and Vicinity Map with 2 km radius landmark

Geodetic Engineer

b. Perspective, Elevation, Floor Plan & Details

Architect

c. Structural Plans

Civil/Structural Engineer

d. Electrical Plans with Details & Computations

Professional Electrical Engineer

e. Plumbing Plans with Details and Isometric View

Master Plumber/Sanitary Engineer if applicable

f. Electronics, Mechanical, Agricultural Plans w/ Details (as needed)

Professional Electronics Communication Engineer, Professional Mechanical Engineer

2. Four (4) Photocopies of Updated Tax declaration

    Municipal Assessor's Office

3. One (1) Copy of Certified True Copy of Land Title and Three (3) photocopies of Original Certificate of Title (OCT)/Transfer Certificate of Title (TCT)

Land Registration Authority – Bukidnon Office

4. Four (4) Photocopies of Authorization from the Land Owner ( duly notarized/ SPA) or Deed of Sale or any proof of ownership if Tax Declaration or Transfer of Certificate of Title (TCT) if not in the name of the applicant)

Owner of the Land

5. Four (4) Photocopies of Current Tax Receipt or Tax Clearance

Municipal Treasurer's Office

6. Two (2) copies of Structural Analysis Design and Computation for 2 storey building or more including high Rise Buildings

Structural/Civil Engineer

7. Two (2) copies of Plate Load Test or Soil Test Analysis for 3 Stories building and above

Geotechnical Engineer

8. Four (4) copies of Notarized Bill of Materials and Cost Estimates

Civil Engineer, Architect

9. Four (4) Photocopies of Building Specifications

Civil Engineer, Architect

10. One (1) Original copy and Two (2) photocopies of the Certification from the Barangay Chairman as to Road Allowance / Construction Clearance ( attached recent photo of the location)

Concerned Barangay LGU

11. Two (2) copies of approved Subdivision Plan/ Sketch Plan of the lot described by the attached Certified True Copy of Title

Department of Environment and Natural Resources (DENR)/Owner of Land

12. One (1) original copy and Two (2) photocopies of the Photocopy of PRC ID & Updated PTR of Practitioners with 3 specimen signed and sealed

Professional Practitioners/Engineers

13. One (1) original copy and Two (2) photocopies of the Certification of Road Right of Way if the location is within the National Highway

Department of Public Works and Highways (DPWH)

14. Locational Clearance

Municipal Planning and Development Office (MPDO)

15. Fire Safety Evaluation Certificate (FSEC)

Bureau of Fire Protection (BFP)

FORMS NEEDED:

1. Five (5) copies of Unified Application Form for Building Permit

OFFICE OF THE BUILDING OFFICIAL

2. Two (2) copies of Application for Locational Clearance/Certificate of Zoning

OFFICE OF THE BUILDING OFFICIAL

3. Two (2) copies of Civil/Structural Permit

OFFICE OF THE BUILDING OFFICIAL

4. Two (2) copies of Architectural Permit

OFFICE OF THE BUILDING OFFICIAL

5. Two (2) copies of Application for Electrical Permit

OFFICE OF THE BUILDING OFFICIAL

6. Two (2) copies of Mechanical Permit

OFFICE OF THE BUILDING OFFICIAL

7. Two (2) copies of Excavation and Ground Permit

OFFICE OF THE BUILDING OFFICIAL

8. Two (2) copies of Application for Sanitary/Plumbing Permit

OFFICE OF THE BUILDING OFFICIAL

9. Two (2) copies of Application for Sign Permit

OFFICE OF THE BUILDING OFFICIAL

10. Two (2) copies of Application for Fencing Permit

OFFICE OF THE BUILDING OFFICIAL

11. Two (2) copies of Application for Electronics Permit

OFFICE OF THE BUILDING OFFICIAL

12. Two (2) copies of Application for Excavation Permit

OFFICE OF THE BUILDING OFFICIAL

13. Two (2) copies of Application for Demolition Permit

OFFICE OF THE BUILDING OFFICIAL

CLIENT STEPS

AGENCY ACTION

FEES TO BE PAID

PROCESSING TIME

PERSON RESPONSIBLE

1 . Submit complete requirements

1.1. Receive and review as to completeness of submitted documents

none

30 minutes

Engineer - I

1.2. Evaluate as to compliance to NBCP (PD 1096 and BP220) and its IRR

NONE

2 HOURS

Engineer - I, MAGH I-OBO

1.3. Endorse one (1) set of required documents to OMPDC for issuance of Locational Clearance

NONE

15 minutes

Engineering Aide

1.4. Endorse three (3) sets of required documents to BFP for issuance of Fire Safety Inspection Certificate (FSIC)

NONE

3 DAYs

Engineering Aide

1.5. Evaluate and issue as to compliance to Fire Safety

NONE

3 DAYS

BFP, CHIEF FSES

1.6. Evaluate as to compliance the Zoning Oridnance

NONE

3 DAYS

Zoning Officer Designate/MPDC-OIC

1.7. Actual Site Inspection and GEO-Tagging

NONE

3 DAYS

Administrative Aide

1.8. Endorse to Bussiness Permit and Licensing Office (BPLO) for Assessment of Contractor's Tax (if the project is implemented by Contract)

LOCAL REVENUE CODE

3 DAYS

BPLO - OIC

2 . Receives the approved Mayor's Clearance from LCE and Approved Building Permit

2.1. Releases the approved Mayor’s Clearance and Approved Buidling Permit

NONE

10 Minutes

Engineer - I / Engineering Aide

TOTAL

NONE

6 Days and 5 Hours