1. Client Request Vehicle/Equipment Repair.Fill up Work Order Request |
Interview Vehicle Driver or Equipment Operator for the Deffects and Complaints. No Major repair for Barangay Government Units. |
None |
10 minutes |
Mechanic I |
2. Client Turn Over Vehicle or Equipment to Motor Pool Shop. |
Mechanic I Diagnose and Trouble shoot Complaints. Report the Findings to Mechanic II for Verification. |
None |
1 Hour |
Mechanic I and Mechanic II |
3. Client Sign Pre repair Inspection Report as requested.Receive the document. |
Prepare Pre Repair Inspection Report. Verify the report and recommendation. Approve the whole Pre repair Inspection Report |
None |
10 minutes |
Mechanic I Mechanic II Supply Officer III/Motor Pool OIC |
4. Client Purchase Spare Parts. Turn Over Purchased items to Motor Pool Shop for the repair |
Check and Receive needed spare parts and schedule the repair . |
None |
10 minutes |
Mechanic II |
5. Wait for the repair to complete |
On Scheduled day or time: Mechanic I repair the unit. Mechanic II test the repaired unit if found okey release the unit to client |
None |
3 Hours (depending on the trouble) |
Mechanic I Mechanic II |
TOTAL |
NONE |
4 hours and 30 minutes |
|