Friday, April 26, 2024

1. ISSUANCE OF MAYOR’S CLEARANCE FOR ELECTRICAL PERMIT

Any person, firm or corporation, including any agency or instrumentality of the government who wants to get a new electrical connection, reconnection, relocation or remodeling of existing electrical installation or for energization of temporary construction facility within the jurisdiction in the Municipality of Manolo Fortich shall apply for an electrical permit.

Service Details

OFFICE OR DIVISION:

OFFICE OF THE BUILDING OFFICIAL

CLASSIFICATION:

SIMPLE

TYPE OF TRANSACTION:

G2C - Government to Citizen

WHO MAY AVAIL:

ALL RESIDENTS OF MANOLO FORTICH, ALL INVESTORS

CHECKLIST OF REQUIREMENTS:

WHERE TO SECURE

1. One (1) original and two (2) photocopies of Sketch of the house containing: a.Front and Rear Elevation b.Floor Plan c.Electrical Plan d.Vicinity/Location plan Note: Duly signed and sealed by Professional Electrical Engineer

Professional Electrical Engineer

2. One (1) original and two (2) photocopies Electrical permit form signed and sealed by a Professional Electrical Engineer and the applicant

Professional Electrical Engineer

3. Three (3) Photocopies of Updated Tax Declaration

Municipal Assessor's Office

4. One (1) Original Copy of Certified True Copy of Land Title and Three (3) photocopies of Original Certificate of Title (OCT)/Transfer Certificate of Title (TCT)

Land Registration Authority

5. Three (3) copies of Authorization from the Land Owner (duly notarized/SPA) or Deed of Sale or any proof of ownership if Tax Declaration or TCT if not in the name of the applicant

Owner of the Land

6. Three (3) copies of Current Tax receipt or Tax Clearance

Municipal Treasurer's Office

7. Three (3) copies of Certification from the Barangay Chairman as to road allowance / Barangay Construction Clearance (attached recent photo of location)

Concerned Barangay LGU

8. Two (2) copies of approved Subdivision Plan/ Sketch Plan of the lot described on the attached Certified True Copy of Original Certificate of Title (OCT)/ Transfer Certificate of Title (TCT)

Department of Environment and Natural Resources (DENR)/Owner of Land

9. One (1) copy of Decision of Zoning and Evaluation Report

Municipal Planning and Development Office (MPDO)

CLIENT STEPS

AGENCY ACTION

FEES TO BE PAID

PROCESSING TIME

PERSON RESPONSIBLE

1 . Submit complete requirements

1.1. Receive and review as to the completeness of submitted documents (Plans & Ancilliary Documents)

None

5 minutes

Engineer - I

1.2. Evaluates as to compliance to PD 1095 and BP 220

None

25 Minutes

Engineer - I

1.3. Endorse one (1) set of required documents to OMPDC for issuance of Locational Clearance

None

10 Minutes

Engineer - I

1.4. Evaluate as to compliance the Zoning Oridnance


2 . Receive Assessment of Fees and Order of Payment

2.1. Issue Order of Payment

None

10 Minutes

Zoning Officer Designate/MPDC-OIC

2.2. Issue Assesment of Fees

Order of Payment shall be based on the schedule of fees prescribed by the National Building Code of the Philippines

10 minutes

Engineering Aide IV

3 . Pay to the cashier

3.1. Receives payment and issue official receipt

Order of Payment shall be based on the schedule of fees prescribed by the National Building Code of the Philippines

5 minutes

REVENUE COLLECTION CLERK II (RCC-II)

4 . Present OR

4.1. Prepares Mayor’s clearance and Locational Clearance

None

20 minutes

Zoning Officer Designate/MPDC-OIC , Enginnering Aide IV

4.2. Endorse to LCE for approval

None

5 Minutes

MAGH I - OBO

4.3. Approves Mayor’’s Clerance

None

1 day

Mayor

5 . Receives the approved Mayor's Clearance from LCE

5.1. Releases the approved Mayor’s Clearance

None

10 minutes

Engineer - I

TOTAL

Order of Payment shall be based on the schedule of fees prescribed by the National Building Code of the Philippines

1 Day, 1 hour and 50 Minutes